解析净化彩钢板的施工步骤
天物彩板专注高端彩板行业16年——江苏净化彩钢板施工安装厂家_净化彩涂卷定制请拨打网站上方电话详细咨询
净化板施工步骤如下:
1看懂图纸,认真检查平面布置、节点要求、净化彩钢板与建筑的关系、彩钢板本身的光泽、填充物及基本尺寸要求、彩钢板隔断内门窗的尺寸及布置等,辅助材料的种类和其他内容。
2二次布置图,这是彩钢板预制安装的重要步骤。将设计图纸转换成中间转换图,供工厂二次加工使用。标准板可在净化彩钢板厂生产,在施工现场组装,既能保证墙板的牢固性,又能加快彩钢板安装速度的发展。
三。在工厂预制时,根据经验,应充分考虑门洞、窗洞和接缝之间的间隙和安装余量。并在运输、生产、安装的全过程中,防止划伤、重压和表面冲击,防止出现不可修复的凹坑和划痕。纯彩钢板两侧的塑料保护膜必须在安装和彻底清洁后才能去除。
4净化彩钢板安装前的放线工作应在地(楼)面层完成后进行,并满足安装的其他相关前提条件,如大型设备已运到位,地面暗管已调好,主体安装工作已完成技术夹层已基本完成。放线是在地面上标出彩钢板的水平投影(50mm宽)和门窗的位置。
5按放样尺寸安装固定铝槽。
6安装干净的彩钢板墙板,按布置图安装预制构件,构件间用固定插件将相邻墙板锁紧。应特别注意壁板的安装和电气暗管、箱盒的配合。墙板应垂直,垂直接缝应紧密。间隙越小,纵缝越美观。操作时,应仔细清理垂直接头上的保护膜,并暂时将其提起,但不得将其取下。清理罐内杂
7清洁彩钢板天花板的安装:顶板的重量支撑是通过固定在周边的垂直板和悬挂在中间的T形铝来实现的。长边缝用固定插件固定加固,短边用T型铝和抽芯铆钉固定。平顶应尽量平整,板缝应密实、均匀、光滑、无痕迹、无破损。控制并注意同一垂直面板。
The construction steps of purification board are as follows:
1. Understand the drawings, carefully examine the plane layout, node requirements, the relationship between the purification color steel plate and the building, the luster, filler and basic size requirements of the color steel plate itself, the size and
layout of doors and windows in the color steel plate partition, the type and other contents of auxiliary materials.
2. Secondary layout drawing, This is an important step in the prefabrication and installation of color steel plate. It is to convert
the design drawings into intermediate conversion drawings which can be used for the second processing in the factory. The standard plates can be produced in the purification color steel plate factory and assembled at the construction site, which can not
only ensure the firmness of the wall panel, but also accelerate the development of color steel plate Installation speed.
3. During prefabrication in the factory, according to experience, the clearance and installation allowance shall be fully considered
between door opening, window opening and seam. And in the whole process of transportation, production and installation, prevent scratch, heavy pressure and surface impact to prevent uncorrectable pits and scratches. The plastic protective film on both
sides of the purified color steel plate can only be removed after the installation and thorough cleaning.
4. The setting out work before the installation of the purified color steel plate should be carried out after the completion of the ground
(floor) surface, and other relevant prerequisites for the installation, such as the large equipment has been transported in place, the concealed ground pipeline has been adjusted, and the main installation work of the technical interlayer has been basically
completed. Setting out is to mark the horizontal projection (50 mm wide) of color steel plate and the position of doors and windows on the ground.
5. Install and fix the aluminum channel according to the lofting size.
6. Erect the clean color
steel plate wallboard, install the prefabricated components according to the layout drawing, and lock the adjacent wall panels with fixed plug-ins between the components. Special attention should be paid to the installation of wall panels and the coordination
of concealed electrical pipelines and boxes. The wall panel should be vertical and the vertical joint should be tight. The smaller the gap is, the more beautiful the vertical joint is. During the operation, carefully clean the protective film on the vertical
joint, and lift it temporarily, but never remove it. Clean the impurities in the tank and the solidified block of adhesive liquid. Otherwise, it is difficult to adjust the vertical joint evenly and compactly with greater force.
7. Installation of
clean color steel plate ceiling: the weight support of the top plate is through the vertical plate fixed at the periphery and T-shaped aluminum suspended in the middle. The long side seam is fixed and reinforced by fixed plug-in, and the short side is
fixed by T-type aluminum and blind rivet. The flat roof shall be leveled as far as possible, and the slab joints shall be dense and even, smooth, free of marks and damages. Control and pay attention to the same vertical panel.